57,000 Tonnes Of Hazardous Materials Finally Dealt With At Dounreay

6/4/2012

Dounreay today completed the destruction of one of the most hazardous legacies of Britain's earliest atomic research.
A purpose-built chemical plant processed the last of 57,000 litres of liquid metal lifted from the primary cooling circuit of the experimental fast breeder reactor.

The coolant - an alloy of sodium and potassium (NaK) - was a major chemical and radiological hazard. An estimated 1000 trillion becquerels of caesium-137 was removed from the coolant during the chemical process that turned the 57 tonnes of liquid metal into 20,000 tonnes of salty water and took four years to complete.

Scotland's Cabinet Secretary for the Environment Richard Lochhead saw the last batches being processed.
He said: "This is a tremendous achievement and another example of how the highly skilled Dounreay workforce is delivering a world-class clean-up operation at one of the most complex nuclear sites in Europe.

"The Scottish Government welcomes today's announcement that Dounreay have successfully destroyed 57,000 litres of highly radioactive liquid metal from the Dounreay Fast Reactor."

The Nuclear Decommissioning Authority said it was "extremely pleased" the liquid metal no longer posed a hazard.
"This was very high on the list of hazards we wanted reduced across our whole estate," said Nigel Lowe, head of the NDA's Dounreay programme. "It's a significant achievement for Dounreay and joins a long list of examples whereby the site has delivered on key objectives and technical challenges."

The reactor - built in the 1950s - was one of only two ever built in Britain to run on liquid metal. Two cooling circuits connected by heat exchangers were filled with more than 161,000 litres of liquid metal.

More than 100,000 litres of NaK from the secondary circuit was destroyed when the reactor shut down in 1977.
Work on the primary circuit - a labyrinth of pipes 9 kilometres in length - stopped in the early 1980s when higher levels of radioactive contamination were detected.

The primary circuit contained 57,000 litres of NaK that flowed over the fuel pins in the reactor core.
The "open vent" design of the fuel cladding allowed the liquid metal to come into direct contact with the fuel, contaminating the primary coolant with huge levels of soluble radioactive caesium. Radiation measurements of the primary coolant showed the presence of 1000 trillion becquerels of caesium-137.

The high level of radioactive contamination added to the chemical hazard of alkali metal that reacts in contact with air or water. Its destruction remained on hold until a decade ago when work started on the construction of a purpose-built clean-up plant. The plant was designed to lift the liquid metal in small batches, neutralise the alkalinity with acid and extract the caesium via ion exchange.

In September 2007, the first of a total of 354 batches was lifted from the reactor. Each batch underwent chemical neutralisation to convert the alkali metal to a salty water before being passed through ion exchange columns that trapped the caesium. Designers thought the plant would decontaminate the effluent by a factor of 1000. Decontamination rates of up to 4 million were achieved during the operation, reducing levels of radioactivity in the effluent to below the limit of detection.

The resin columns used to trap the caesium will now be cemented up and managed as higher-activity waste.
"It's been a fantastic achievement by the whole team to deliver this milestone a year ahead of schedule and to higher environmental standards than anyone thought possible at the design stage," said Andy Swan, the engineer in charge of the reactor decommissioning.

"This stuff was highly volatile and highly radioactive. The chemical and radiological hazards combined to make this a real danger to the workers involved, so we needed to be certain they were protected at every step of the process until the hazard was destroyed. Their safety record throughout this operation was excellent."

Destruction of the liquid metal was among the strategic national priorities of the Department of Energy and Climate Change, which sponsors the Nuclear Decommissioning Authority.

With the reactor vessel empty of liquid metal, attention now turns to cleansing the residual traces from the primary circuit pipework and destroying small pockets in other vessels. When complete, a robotic arm will reach into the reactor vessel and begin removing the burst fuel pin and almost 1000 breeder elements still positioned around the core.

 

Related Businesses

 

Related Articles

NDA decommissioning supply chain event returns
The NDA estate's showcase event for suppliers is returning for a fourth year and is looking forward to welcoming even more visitors and exhibitors.   More than 1,000 delegates from across the country attended the 2013 event, including existing supply chain members and decommissioning newcomers.  
Radioactivity Found In A Drainage System Near Dounreay
The Environmental Closure & Demolition department at Dounreay have found elevated levels of radioactivity in a manhole in a redundant offsite drainage system.   Samples of sludge were taken from the manhole which indicated elevated levels of alpha activity.  
Dounreay revises site closure plansThumbnail for article : Dounreay revises site closure plans
Two years into its major contract to complete the clean-up and shutdown of Dounreay, the consortium in charge of Dounreay Site Restoration Ltd is now revising its programme of work to accommodate changes being made by the Nuclear Decommissioning Authority.   The NDA awarded a contract in April 2012 to Cavendish Dounreay Partnership.  
New civilian guard force to be created at Dounreay
DSRL has announced that it will be creating a new civilian guard force at Dounreay.   The news comes after discussion between the Department of Energy and Climate Change, the Nuclear Decommissioning Authority, the Office for Nuclear Regulation’s Security department, the CNC and DSRL.  
NDA sets key tasks for 'role model' DounreayThumbnail for article : NDA sets key tasks for 'role model' Dounreay
Dounreay’s owners have set out their priorities for decommissioning in a three-year business plan approved by Ministers.  The Nuclear Decommissioning Authority, which owns Dounreay and 16 other sites in the UK, has total planned expenditure across its estate for 2014/15 of £3.2 billion.  
[Marine Services]14/3/2014
Heavy Lift Pad Construction Underway At Wick HarbourThumbnail for article : Heavy Lift Pad Construction  Underway At Wick Harbour
Wick Harbour Authority is making progress with its plans to create a heavy-lift facility on the commercial quay at Wick harbour, with contractors Gunns Lybster Ltd having now begun the work.   The project, and its associated dredging works, was supported by CNSRP partners HIE and NDA respectively and is the first of several proposed phases of work to position the harbour as a key player in the energy sector, with the current focus being on potential to benefit from the development of Offshore Wind in the Moray Firth.  
Reactor demolition takes another step forward at DounreayThumbnail for article : Reactor demolition takes another step forward at Dounreay
A pioneering Dounreay innovation has allowed the team taking apart the Prototype Fast Reactor to complete one of the final phases ready for demolition.   The centre guide tube - which once housed the reactor's control and shutoff rods - was successfully raised from the reactor core, demonstrating that internal fixtures can be safely removed.  
Minister sees Dounreay decommissioning first handThumbnail for article : Minister sees Dounreay decommissioning first hand
Dounreay welcomed Fergus Ewing MSP, Minister for Energy, Enterprise and Tourism to see the world leading decommissioning work taking place at the site.   He also met with Andrew Wettern, business development director for Cavendish Nuclear, who was accompanying Hidehiro Segawa of Hitachi-GE Nuclear Energy on his knowledge sharing and fact finding visit to the site.  
Supply chain invited to attend free workshop
DSRL will be running a free workshop to train the supply chain on the new Complete Tender Management (CTM) system.   The workshop will be held on Thursday February 20, 2014 at the North Highland College, Thurso from 1pm to 4pm.  
Dounreay Jobs Will Last Longer Than Previously ThoughtThumbnail for article : Dounreay Jobs Will Last Longer Than Previously Thought
Management at Dounreay are facing the challenge of how to accommodate additional work from the Nuclear Decommissioning Authority (NDA) whilst maintaining the same annual spend, the same Interim End State and most importantly, the same priority on working safely and securely that the site is renowned for.   The additional work has arisen because activities that were not sufficiently developed by the NDA at the time the competition was run in 2012 have now reached a state of maturity that allows them to be added to the existing programme of work.  