£2million Plan For Closure At Landfill Site
15/1/2011
Dounreay Site Restoration Ltd wants to restore an area of land designated as a rubble dump during the construction and operation phases of the site.
An estimated 70,000m3 of material from the construction and demolition of buildings was deposited in the area beyond the eastern perimeter of the site from 1960 or so.
The site, known as Landfill 42, was taken out of use in 2005 and needs to be restored under environmental and planning regulations.
This will involve repositioning approximately 16,000m3 of material and the construction of a new sea defence. A substantial impermeable membrane and an estimated 25,000 tonnes of rock will be used in the closure works.
The work is expected to cost £1-2 million and, subject to regulatory controls, is due for completion by the end of 2011.
Gas and groundwater monitoring will continue for a number of years after restoration until the licence can be surrendered to the Scottish Environment Protection Agency.
The landfill is known to contain hazardous materials, including metals, asbestos and minor radioactive pollution from ground excavation and building demolition work dating back to the 1960s and 1970s.
Phil Cartwright, contaminated land manager at DSRL, said extensive work had been carried out in recent years to characterise the facility.
"We studied several options for closure of the landfill and carefully considered the environmental impact of each," he said.
"We believe the facility can be left in a safe condition with the engineering measures identified in our closure application to the Scottish Environment Protection Agency."
The landfill is adjacent to ground now being developed as a site for the disposal of low-level radioactive waste from decommissioning the site.£2million Closure Plan For Landfill site
Related Businesses
Related Articles
A camera has delved into the depths of Dounreay’s famous dome and captured the first footage for over fifty years of Britain’s first Fast Breeder Reactor. Nitrogen cooled digital cameras have been inserted into the reactor and recorded the images of the internal structures and the breeder fuel matrix. ... [
full story]
The Nuclear Decommissioning Authority (NDA) has this week published its 2013-16 Business Plan which sets out its delivery priorities for the period as it continues to focus on accelerating hazard reduction across its 19-site estate. The focus at Sellafield will remain on driving forward further progress across the site including a programme of major projects required to decommission the high hazard legacy ponds and silos, while also working towards the completion of the contracts at both the Magnox and Thorp reprocessing plants by the end of the decade. ... [
full story]
The Nuclear Decommissioning Authority (NDA) has announced a decision to proceed with the next phase of the National Nuclear Archive project, which will see a new purpose built archive facility constructed at Wick to provide long-term storage of records and other archive material from civil nuclear sites in the UK. The archive will be operated on NDA’s behalf by a specialist commercial partner and is expected to bring more than 20 sustainable jobs to the town. ... [
full story]
The Nuclear Decommissioning Authority says significant acceleration in the clean-up and shutdown of Dounreay will bring real value to the taxpayer who funds the work. Its chief executive John Clarke, writing in the organisation's annual report published today, says the award of the site closure contract earlier this year was a milestone in the NDA's mission to clean up the UK's nuclear legacy and bring down the cost. ... [
full story]
As the opportunities for renewable energy increase in the North of Scotland, the lead partner in the Dounreay site, Babcock, announces its continued support to bring jobs into the area. The secondment of June Love, Dounreay, to support Highlands and Islands Enterprise (HIE) activities in the sectors of Energy and Business Services demonstrates a real partnership working between the private and the public sectors. ... [
full story]
Dounreay today completed the destruction of one of the most hazardous legacies of Britain's earliest atomic research. A purpose-built chemical plant processed the last of 57,000 litres of liquid metal lifted from the primary cooling circuit of the experimental fast breeder reactor. ... [
full story]
Construction work is underway on a new railhead to support the closure of the redundant nuclear site at Dounreay. The facility at Georgemas Junction on the far north rail line will enable fuel belonging to the UK to be returned to national stocks where it can be used to generate electricity. ... [
full story]
The Nuclear Decommissioning Authority today publishes its business plan for 2012/13, setting out key clean-up goals for sites such as Dounreay to achieve. "Our business plan for 2012/2013 sees us entering into the second year of funding allocated in the last spending review," says NDA chief executive John Clarke. ... [
full story]
Senior figures from government and industry are gathering at Dounreay today to hear the site's new clean-up team set out their vision to accelerate the demolition of Britain's second largest civil nuclear site. Three of the world's biggest engineering and project management companies - Babcock International, CHM2HILL and URS - have come together to win the largest site closure contract ever let in the UK. ... [
full story]
Dounreay Site Restoration Ltd is under new ownership from today. The company is now a wholly-owned subsidiary of the Babcock Dounreay Partnership. ... [
full story]
[Printer Friendly Version]